#11 netoffice uses due dates instead of real dates

open
nobody
None
5
2009-10-11
2009-10-02
士 天龙
No

If we were tracking projects we want to see the real behavior not the planned or ideal behavior, if a task was completed two weeks before its due date all the dependant tasks really start two weeks later, but netoffice keep showing them as started in the ideal due date.

Ths is an error.

How to reproduce it.

Create two tasks,, add an ancestor with 0 lag, finish to start.
Then complete the ancestor two weeks later. Go and check the gantt diagram and see that the second task is starting in the due date instead two weeks later the due date. You have to manually add a lag or something, but of course if you are using a tool the tool must care about it.

Discussion

  • Luis, Wang

    Luis, Wang - 2009-10-08
    • status: open --> pending-wont-fix
     
  • 士 天龙

    士 天龙 - 2009-10-11
    • status: pending-wont-fix --> open
     
  • 士 天龙

    士 天龙 - 2009-10-11

    Also the same problem occurs if you finish a task earlier, you can move forward and start other tasks with 0 lag too, but gantt diagrams keep showing the start later than the available start

     