MS Project 2010: tasks with null baseline dates
Multi platform library to read and write schedule data
Brought to you by:
joniles
I have this problem when MPXJ reads .MPP files saved on MS Project 2010.
I define baseline start and finish for all tasks in my projects using MS Project 2010. When I open the files with MPXJ, some of the tasks come with null baseline start or null baseline finish.
I am using the MPXJ 4.7.3, but I also found this behavior in other application which uses the 4.5.0-rc1 version.
I attached a snapshot of the tasks that come either with null baseline start or null baseline finish.
It is important to say that when I perform the same procedure in MS Project 2007 everything goes fine. All the fields are correctly read by both MPXJ versions.
The changes now in Git fix this issue.