#259 MS Project 2010: tasks with null baseline dates

v1.0_(example)
closed-fixed
Jon Iles
5
2015-02-10
2015-02-04
No

I have this problem when MPXJ reads .MPP files saved on MS Project 2010.

I define baseline start and finish for all tasks in my projects using MS Project 2010. When I open the files with MPXJ, some of the tasks come with null baseline start or null baseline finish.

I am using the MPXJ 4.7.3, but I also found this behavior in other application which uses the 4.5.0-rc1 version.

I attached a snapshot of the tasks that come either with null baseline start or null baseline finish.

It is important to say that when I perform the same procedure in MS Project 2007 everything goes fine. All the fields are correctly read by both MPXJ versions.

2 Attachments

Discussion

  • Jon Iles

    Jon Iles - 2015-02-10

    The changes now in Git fix this issue.

     
  • Jon Iles

    Jon Iles - 2015-02-10
    • status: open --> closed-fixed
    • assigned_to: Jon Iles
     