Menu

#241 Not able to set Actual Work in MSP2010 and also not able to set milestone as complete

v1.0_(example)
open
nobody
None
5
2014-05-14
2014-05-14
No

Hi

First of all thank you very much for MPXJ library. It helped us really well in our integration. I am in the last stage of it and somehow not able to figure out how to resolve following 2 issues. We are setting Milestone as complete but not able to do so. For setting milestone as 100 percent complete. I am setting below values as shown below:

task.setActualStart(projItem.getResolutionDate().getTime());
task.setActualFinish(projItem.getResolutionDate().getTime());

These two value set the milestone as complete as per my analysis. I tried setting percentcomplete ,stop,resume value. But still when xml is generated its not setting these values.

Also whenever I set the actual work and work value for any task it sets the whole task as complete. I am not sure how to fix these two problems. Request your help here. Thanks.

Discussion


Log in to post a comment.

Monday.com Logo