In version 4.4 when opening 2013 files all tasks have the milestone value set on true and the schedule mode set on "Manual schedule".
Thanks, Tibi
Can you provide a sample file with a note on what the expected values should be?
Thanks!
Jon
It seems that the problem also appears on 2010 files. Please see the attached file. All tasks are manual scheduled when some of them should be automatically scheduled. Also all tasks are milestones when they have a not zero duration.
And the same behavior is present in issue https://sourceforge.net/p/mpxj/bugs/224/ where is attached another sample file.
Tibi
The patch from issue https://sourceforge.net/p/mpxj/bugs/224/ indeed solves the milestone problem. But it still remains the task mode problem.
I believe this issue is fixed for Project 2013 files by the latest code in Git.
Yes the problem is solved.
Is the Auto/Manual scheduled information accessibe with 4.4 ? if so, please indicate the API.
Log in to post a comment.
Can you provide a sample file with a note on what the expected values should be?
Thanks!
Jon
It seems that the problem also appears on 2010 files. Please see the attached file. All tasks are manual scheduled when some of them should be automatically scheduled. Also all tasks are milestones when they have a not zero duration.
Thanks,
Tibi
And the same behavior is present in issue https://sourceforge.net/p/mpxj/bugs/224/ where is attached another sample file.
Tibi
The patch from issue https://sourceforge.net/p/mpxj/bugs/224/ indeed solves the milestone problem. But it still remains the task mode problem.
Tibi
I believe this issue is fixed for Project 2013 files by the latest code in Git.
Yes the problem is solved.
Is the Auto/Manual scheduled information accessibe with 4.4 ? if so, please indicate the API.