When the project has resources and resource calendar, the order in the mpx file was wrong. all resource calendar get the number 20,25and 26 not the needed number 55.56 and 57.
Record name Record number Maximum number of Records
----------------------------------------------------------------------------
File Creation (required) none 1
Currency Settings 10 1
Default Settings 11 1
Date and Time Settings 12 1
Base Calendar Definition 20 250
Base Calendar Hours 25 7 per Base Calendar
Definition record
Base Calendar Exception 26 250 per Base Calendar
Definition record
Project Header 30 1
Text Resource Table Definition 40 1
(Or you can use the Numeric Resource Table Definition record)
Numeric Resource Table Definition 41 1
Resource 50 9,999
Resource Notes 51 1 per Resource record
Resource Calendar Definition 55 1 per Resource record
Resource Calendar Hours 56 7 per Resource Calendar
Definition record
Resource Calendar Exception 57 250 per Resource Calendar
Definition record
Text Task Table Definition 60 1
(Or you can use the Numeric Task Table Definition record)
Numeric Task Table Definition 61 1
Task 70 9,999
Task Notes 71 1 per Task record
Recurring Task 72 1 per Task record
Resource Assignment 75 100 per Task record
Assignment Workgroup fields 76 1 per Assignment record
Project Names 80 500
DDE and OLE Client Links 81 500
Comments 0 unlimited
View and moderate all "bugs Discussion" comments posted by this user
Mark all as spam, and block user from posting to "Bugs"
I think I've fixed this, can you try the code in CVS to see if it does what you expect?
Thanks!
Jon
I've had no feedback on this item, so I'm goig to assume the fix has been successful and close the item.