The MPXJ API seems to return the incorrect start date of a manually scheduled task. Looks like, it always returns the
project's start date instead. Is there a workaround for this, or is it a bug?
We are trying to ship a product using MPXJ. This issue is impacting our ability to ship a reliable import/export solution for MS Project 2010. Is there anything we can do to influence this issue being resolved. We are code complete in QA now.
Thank you,
Greg Ames
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
You should find that the code now in CVS fixes this. Let me know if you have any further problems. If you are using MPXJ as part of a piece of commercial software it's always worth dropping me a note directly as well as raising the issue in the bug tracker - I will be able to respond more quickly to you.
Cheers!
Jon
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
We are trying to ship a product using MPXJ. This issue is impacting our ability to ship a reliable import/export solution for MS Project 2010. Is there anything we can do to influence this issue being resolved. We are code complete in QA now.
Thank you,
Greg Ames
I'm looking at it now, bear with me.
You should find that the code now in CVS fixes this. Let me know if you have any further problems. If you are using MPXJ as part of a piece of commercial software it's always worth dropping me a note directly as well as raising the issue in the bug tracker - I will be able to respond more quickly to you.
Cheers!
Jon