Other TimePhased Data
I know this has been open a very long time, but just to confirm that MPXJ 16.0.0 is now available which has significant improvements in timephased data handling, including rollup to the Task and Resource level.
using mpxj latest library 5.2.2 the assignment timephasedbaseline values are not correct
I know this has been open a very long time, but just to confirm that MPXJ 16.0.0 is now available which has significant improvements in timephased data handling. Hopefully you'll find that this issue is now fixed.
Calendar getDate With Negative Duration
Just tidying up old issues, but to confirm thatthe getDate method in the most recent MPXJ releases should handle both positive and negative values correctly.
Wrong timephased data when importing from mpp
I know this has been open a very long time, but just to confirm that MPXJ 16.0.0 is now available which has significant improvements in timephased data handling. Hopefully you'll find that this issue is now fixed.
Incorrect values for start, finish and duration tasks for MPP file
I've made some changes to MPXJ to accommodate this. The notes on this pull request https://github.com/joniles/mpxj/pull/762 give some more details. In sumary, there rae new task methods, getShowStartText, getShowFinishText and getShowDurationText, which you can use to determine if you show the normal attribute (e.g. Start) or the text attribute (e.g. StartText). This should give you the output you expect.
Incorrect values for start, finish and duration tasks for MPP file
Incorrect values for start, finish and duration tasks for MPP file
ResourceAssignment is not added when exporting to Primavera in MSPDI format
Hello! I think you've opened the same issue over on GitHub, let's use that one and I'll close this one.
ResourceAssignment is not added when exporting to Primavera in MSPDI format