First of all, congrats on the project it looks great!
I would like to know if it is possible to schedule tasks according to constraints and resource availability ?
I can look at the resource load and manually move tasks around and/or add more resources but it would be nice to be able to just add a list of tasks and resources and have libreplan schedule the project in a feasible manner.
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
we're sorry but currently it's not possible to do such automatic planning in NavalPlan.
The only similar feature would be create a list of tasks with hours, set resources for each task, add the proper dependencies on Gantt and use reassign button
Hi,
First of all, congrats on the project it looks great!
I would like to know if it is possible to schedule tasks according to constraints and resource availability ?
I can look at the resource load and manually move tasks around and/or add more resources but it would be nice to be able to just add a list of tasks and resources and have libreplan schedule the project in a feasible manner.
Hi,
we're sorry but currently it's not possible to do such automatic planning in NavalPlan.
The only similar feature would be create a list of tasks with hours, set resources for each task, add the proper dependencies on Gantt and use reassign button
If you have any other question you can chat with us at #navalplan IRC channel in Freenode: http://webchat.freenode.net/?channels=#navalplan
Thanks you for testing NavalPlan,
Rego