Scheduling based on resources

2011-09-05
2012-11-26
  • Nelson Silva

    Nelson Silva - 2011-09-05

    Hi,

    First of all, congrats on the project it looks great!

    I would like to know if it is possible to schedule tasks according to constraints and resource availability ?

    I can look at the resource load and manually move tasks around and/or add more resources but it would be nice to be able to just add a list of tasks and resources and have libreplan schedule the project in a feasible manner.

     
  • Manuel Rego Casasnovas

    Hi,

    we're sorry but currently it's not possible to do such automatic planning in NavalPlan.

    The only similar feature would be create a list of tasks with hours, set resources for each task, add the proper dependencies on Gantt and use reassign button

    If you have any other question you can chat with us at #navalplan IRC channel in Freenode: http://webchat.freenode.net/?channels=#navalplan

    Thanks you for testing NavalPlan,
       Rego

     