#1 Types of tasks connections

open
nobody
None
5
2002-01-23
2002-01-23
No

In the current version, the tasks are linked only with
a finish-start connection type.
|----task1----|
|-task2-|

Allow to choose start-start
|----task1----|
|-task2-|
or finish-finish
|----task1----|
|-task2-|

Discussion

  • Christian Garbs

    Christian Garbs - 2002-01-24

    Logged In: YES
    user_id=36210

    Right now we are working towards the first major release
    (it will probably be v0.2.0).

    When we are done with that, we will take a look at your (and
    other's) feature requests that we have received so far and
    decide what to do, what to do later and what to do not at all.

    So thanks for your request, it won't be lost. Just delayed.

     
  • Nobody/Anonymous

    Logged In: NO

    I would like to add that sometimes there is need for a small
    delay between a task and another:

    |--task1--|
    (3)--> |--task2--|

    Here, task2 starts 3 days after beginning of task1

     

Log in to post a comment.