Sometimes when a sync job is finished, the progress bar says and shows 100%. Often, it shows an old status that doesn't update. Right now, the example I'm looking at shows 50:53 / 51:22 on the top bar and about 1/3 complete on the bottom bar. The messages tab shows that the job is complete.

Discussion

  • Bill

    Bill - 2012-11-16
     
  • Tau

    Tau - 2012-12-26

    This happens with v1.45 on my notebook and also on an desktop PC. How much is left out (not filled) seems to depend the on the amount of the files in the job. The v 1.44 did not have this problem at all.

    XP SP3, Java 1.7.0-09-b05

     
  • O. Givi

    O. Givi - 2013-10-03
    • status: open --> closed-fixed
    • assigned_to: O. Givi
    • Group: --> All versions
     
  • O. Givi

    O. Givi - 2013-10-03

    Fixed.

     