Task A using resource A finishes at 4pm. Task B is dependent on Task A but uses a different resource. Assuming resource B is available, Task B starts at 9.00 am, because only the day is checked
This is documented as a limitation on the wiki:
http://deplan.wiki.sourceforge.net/Levelling#limitation