I used F9 to recalculate, and the task will not move.
This task may have a "fixed" date of some kind. Use the Tasks with Fixed Dates Filter to view only those tasks in a plan that contain fixed dates. You can then remove the fixed dates, if desired.
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
I used F9 to recalculate, and the task will not move.
This task may have a "fixed" date of some kind. Use the Tasks with Fixed Dates Filter to view only those tasks in a plan that contain fixed dates. You can then remove the fixed dates, if desired.