kalo wand - 2013-04-08

Hi All,

as I know any manufacturing workflow includes activities and operations (nodes), but when u create a manufacturing order and order receipt & issue, u create this at the level of the whole workflow not at the level of the activity or the operation.

For example; the MO x includes the activities n,m,o . in the activity n we need raw material a,b from the warehouse , use resources and use asset c. after I issue the raw material a and b, resources and asset c.the activity n should be closed Then the activity m start,,,,etc, at the last activity o the Mo should be closed.

Thus, how can we start or close certain activity or operation included in the workflow?
In other words, how can we create Work order for certain operation that requires resources/work centers or raw material from the warehouse?
I wish I could elaborate my case.

thanks