#47 DPPT Test Plan errors

Should_Fix
open
Test Plan (6)
1
2012-07-18
2001-06-25
Marty Hoag
No

The dppt test plan (dppt_tplan_6.xls) has a few errors/typos and ambiguities listed below.

TC #8: Says "Press PGDN key" but should be "Press PGUP key" to go backwards to return to the
first slide.

TC # 17, 18: I assume this refers to wmaster but I think it should specify that. When I ran
wclient I got a borderless display window on the operator control screen and the other window
with the various menus on my display projector where ppt usually runs (I usually just use client). I
could NOT find a way to move and resize the wclient display window while it was running.

TC # 21, 22: I think there should be an execution step to actually RUN the masterpos.bat and
clientpos.bat after modifying since this is different than how the config.bat file works. ;-)
Also, it seems there are some execution steps in the test condition (edit is an execution step for
example).

TC # 39: It is probably obvious but since 38 is a registry/server test I wonder if the tester should
be reminded to establish normal registry/agserv operation after case 38.

TC # 43: the last line is a "lineo" which I think was copied from previous cell - strike the "without
using full path" line (assuming #43 should match #42).

TC # 67: Should be eliminated or changed to "Open MS IE on display machine" since Netscape is
no longer used/required on Display machine.

There are also some minor issues with the test case specifying to run previous steps and others
where that isn't done (e.g. TC#s 12, 13). Also, there are several combinations of where server,
master, and client all run which are not really specified and may not really make any difference
anyway.

Anyway, DPPT seemed to work as expected.

Marty