Does anyone knows that BOM Product price is depend of the price of the products which built it. For example Product A consist of 1 product B and 1 product C. Product B and C are being priced at USD 5 and USD 6 respectively. The price of Product A would be USD 11. You cannot change it.
Meanwhile we often find a case where the price of Product A IS NOT the price of product B or C combined. It can be higher or lower. I try to add price to product A, which not the combined price but it doesn't work. This is what happen.
I put price of USD 15 for product A. When I created Sales Order, and I chose product A the price was still USD 15. Everything felt right. And then the disaster came. When I click Complete button suddenly the price change to USD 11!
Any help for this one? Btw, I'am using Compiere 3.0.1
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
if the BOM is not stocked it is considered a 'basket; and will compute the price based on the component prices. If you want to assign a price change it to 'stocked'
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Dear OpenSourceMan and Adhitya , Kathy Pink:
>> if the BOM is not stocked it is considered a 'basket;
>> and will compute the price based on the component prices.
>> If you want to assign a price change it to 'stocked'
This is a way but not really status for company., because the product is not 'stocked' !!
>> For example Product A consist of 1 product B and 1 product C.
>> Product B and C are being priced at USD 5 and USD 6 respectively.
>> The price of Product A would be USD 11.
>> You cannot change it.
If Non-'stocked' A = 'stocked' B + 'stocked' C + 'stocked' the service D must add-on
Theb 15 = 6 + 5 + 4(service charge)
ERP is not for get result balance only,
ERP is management not calculate,
Take over Compiere you need Albert
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
I am new user of compiere2. Sir can you provide me compiere2 database backup and
Importcompiere2.bat file. Both file is not in my comoiere2 folder. Because you currently running this S/w in your Orignazation so please help me for getting the both file.
yours,
sanjeev kumar
send some info. in the following mail id also.
sanjeev_bokaro@rediffmail.com
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
>>And then the disaster came. When I click Complete button suddenly the price change to USD >>11!
Sounds like the price hadn't still been updated after the last change. At least in Compiere 2.61 I'm using, it's a good habit to do Cache Reset every now and then, because it can save you from a lot of trouble.
For the actual BOM price, Compiere offers more than one choice; it can bee a sum of the products it's comprised of, or you can set it to be something else. Please refer to the relevant section in the manual.
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
Does anyone knows that BOM Product price is depend of the price of the products which built it. For example Product A consist of 1 product B and 1 product C. Product B and C are being priced at USD 5 and USD 6 respectively. The price of Product A would be USD 11. You cannot change it.
Meanwhile we often find a case where the price of Product A IS NOT the price of product B or C combined. It can be higher or lower. I try to add price to product A, which not the combined price but it doesn't work. This is what happen.
I put price of USD 15 for product A. When I created Sales Order, and I chose product A the price was still USD 15. Everything felt right. And then the disaster came. When I click Complete button suddenly the price change to USD 11!
Any help for this one? Btw, I'am using Compiere 3.0.1
if the BOM is not stocked it is considered a 'basket; and will compute the price based on the component prices. If you want to assign a price change it to 'stocked'
Dear OpenSourceMan and Adhitya , Kathy Pink:
>> if the BOM is not stocked it is considered a 'basket;
>> and will compute the price based on the component prices.
>> If you want to assign a price change it to 'stocked'
This is a way but not really status for company., because the product is not 'stocked' !!
>> For example Product A consist of 1 product B and 1 product C.
>> Product B and C are being priced at USD 5 and USD 6 respectively.
>> The price of Product A would be USD 11.
>> You cannot change it.
If Non-'stocked' A = 'stocked' B + 'stocked' C + 'stocked' the service D must add-on
Theb 15 = 6 + 5 + 4(service charge)
ERP is not for get result balance only,
ERP is management not calculate,
Take over Compiere you need Albert
Hi sir,
I am new user of compiere2. Sir can you provide me compiere2 database backup and
Importcompiere2.bat file. Both file is not in my comoiere2 folder. Because you currently running this S/w in your Orignazation so please help me for getting the both file.
yours,
sanjeev kumar
send some info. in the following mail id also.
sanjeev_bokaro@rediffmail.com
>>And then the disaster came. When I click Complete button suddenly the price change to USD >>11!
Sounds like the price hadn't still been updated after the last change. At least in Compiere 2.61 I'm using, it's a good habit to do Cache Reset every now and then, because it can save you from a lot of trouble.
For the actual BOM price, Compiere offers more than one choice; it can bee a sum of the products it's comprised of, or you can set it to be something else. Please refer to the relevant section in the manual.