Donate Share

Task Coach

Tracker: Bugs

1 Add Task - Categories - ID: 2806354
Last Update: Comment added ( sf-robot )

In the "Add Task" dialog box, after I've named my new task, I then go to
the Categories screen and choose a category and it appears to accept this
information. However, when I return to my "tree of tasks," the category
that I'd chosen is not identified. I can add the category by right-clicking
and toggle a category. Not sure if this is a bug or by design.


airolgmd ( airolgmd ) - 2009-06-15 00:40

1

Closed

Fixed

Frank Niessink

Windows

Release 0.73.0

Public


Comments ( 10 )

Date: 2009-11-22 02:20
Sender: sf-robotSourceForge.net Site Admin

This Tracker item was closed automatically by the system. It was
previously set to a Pending status, and the original submitter
did not respond within 14 days (the time period specified by
the administrator of this Tracker).


Date: 2009-11-07 10:56
Sender: fniessinkProject AdminAccepting Donations

This bug should be fixed in the latest release of Task Coach. Can
you please install the latest release of Task Coach and confirm
that this bug has indeed been fixed?

Thanks, Task Coach development team


Date: 2009-10-28 21:13
Sender: fniessinkProject AdminAccepting Donations

Hi,

I fixed a refreshing issue that might be related to this bug report.
Please test if you have the time (see the other notice).

Thanks, Frank


Date: 2009-10-28 21:13
Sender: fniessinkProject AdminAccepting Donations

A fix was made and checked into the source code repository of Task Coach.
The fix will be part of the next release. You will get another notification
when that release is available with the request to install the new release
and confirm that your issue has indeed been fixed.

If you like, you can download a recent build from
http://www.fraca7.net/TaskCoach-packages/latest_bugfixes.py to test the
fix.

Because a fix has been made for this bug report, the priority of this
report has been lowered to 1 and its resolution has been set to 'Fixed'.

Thanks, Task Coach development team


Date: 2009-06-15 20:00
Sender: airolgmd

I chose an existing category. Not identified=blank, empty field <grin>

This seems to have mysteriously righted itself. I can't duplicate it now,
either. I know it wasn't working for quite a few tasks before.


Date: 2009-06-15 20:00
Sender: airolgmd

To better investigate the bug you reported we'd like you to supply more
information. On the bug report form, please enter the Task Coach release
you are using (in the 'Group' field) and the platform that you are on (in
the 'Category' field).

Thanks, Task Coach development team


Date: 2009-06-15 19:07
Sender: fniessinkProject AdminAccepting Donations

Hmm, it turns out I was able to replicate the issue exactly once. Whatever
I do I can't seem to trigger it a second time.

By the way, do you choose an existing category or do you create a new one
in the categories tab of the task edit dialog? And what do you mean by "the
category that I'd chosen is not identified"?

Thanks, Frank


Date: 2009-06-15 18:20
Sender: fniessinkProject AdminAccepting Donations

We could reproduce the bug you reported. We'll do our best to fix it as
soon as possible.

Thanks, Task Coach development team


Date: 2009-06-15 01:00
Sender: airolgmd

I take that back, I can't "toggle" and right-click, I have to actually edit
the task.


Date: 2009-06-15 01:00
Sender: airolgmd

To better investigate the bug you reported we'd like you to supply more
information. On the bug report form, please enter the Task Coach release
you are using (in the 'Group' field) and the platform that you are on (in
the 'Category' field).

Thanks, Task Coach development team


Attached File

No Files Currently Attached

Changes ( 9 )

Field Old Value Date By
status_id Pending 2009-11-22 02:20 sf-robot
close_date 2009-11-07 10:56 2009-11-22 02:20 sf-robot
allow_comments 1 2009-11-22 02:20 sf-robot
status_id Open 2009-11-07 10:56 fniessink
close_date - 2009-11-07 10:56 fniessink
priority 4 2009-10-28 21:13 fniessink
resolution_id None 2009-10-28 21:13 fniessink
assigned_to nobody 2009-06-15 18:20 fniessink
priority 5 2009-06-15 18:20 fniessink