Using the PreRequisites

Evanzab
2014-05-07
2014-05-08
  • Evanzab
    Evanzab
    2014-05-07

    Hi,
    I can't seem to figure out how to assign one task to be the prerequisite of another task. How is this done? Also, what happens when you try to 'Start Tracking Effort' on a task that doesn't have its prerequisites fulfilled?
    Thanks!
    -Evan

     
  • Evanzab
    Evanzab
    2014-05-08

    I figured out that it had the hide inactive tasks filter on, and i hadn't made any active yet.

    It appears there is nothing that prevents making a task active or tracking effort if the prerequisite has not been met. Is there a way to get it to do something like prevent it or pop up a warning that the pre-req has not been met yet?