Incorrect date changing?

Bug List
d47
2013-10-26
2013-10-26
  • d47
    d47
    2013-10-26

    Here is a video of updating actual work for a task. Notice how setting actual work from partial work back to 0, which should be expected in editing and updating a project, moves forward dates in the project continually. Even when all the data is the same.

    http://screencast.com/t/s4m9wD8DqS

    All task are linked using the normal FS linking method in the Gannt Chart. Resetting the dependencies by removing them then relinking shows the expected result, the same way the project started.

     
    Last edit: d47 2013-10-26