Resource histogram display

Bug List
sbs
2014-02-05
2014-02-05
  • sbs
    sbs
    2014-02-05

    When displaying the resource histogram, resource availability shows 100% and 0% for work days or week ends. Then when zooming out to the week level, resource availability is at 70%. Which I assume averages work days and week-ends. I do not understand why the availability changes with zoom level.
    When zooming out to the month level, its even worse, since the resource oscilate depending on the amoun of work day in the month.

    Is this a bug or a misunderstanding on my side? At the extreme, I could argue that 8h work a day is only 30% and as such availability should be 30% and not 100% on work days. Shouldn't the availability computation use the resource calendar to only take into account the worked periods. So that the zoom level would not affect the availability value?

     