I have created the project called "PROJECT01" and created all the tasks. After I reopen the task , I am unable to see the tasks. It throws the error as
Error:
can't read "row(tree_order)": no such element in array
Kindly help me out.
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
We would need to reproduce this issue in order to be able to fix it. We've checked for "tree_order", but that only appears on a deep-down system routine.
The most likely cause is that you did something strange in the definition of your tasks, thus creating an exceptional situation that's not handled by the system routine.
=> Please send use the MS-Project schedule that you imported or try to reproduce on one of our demo servers.
Sorry, we can't help more...
Frank
If you would like to refer to this comment somewhere else in this project, copy and paste the following link:
I am using the latest version 4.0.
I have created the project called "PROJECT01" and created all the tasks. After I reopen the task , I am unable to see the tasks. It throws the error as
Error:
can't read "row(tree_order)": no such element in array
Kindly help me out.
I once experienced this err message related to a memory issue. Can you try to restart the webserver before we have a closer look?
Hi Klaus,
As you said, I restarted the server and tried. Again the same error.
Timesheet Tasks
Error:
can't read "row(tree_order)": no such element in array
Help me please.
Last edit: svl 2015-05-19
Hi!
We would need to reproduce this issue in order to be able to fix it. We've checked for "tree_order", but that only appears on a deep-down system routine.
The most likely cause is that you did something strange in the definition of your tasks, thus creating an exceptional situation that's not handled by the system routine.
=> Please send use the MS-Project schedule that you imported or try to reproduce on one of our demo servers.
Sorry, we can't help more...