Menu

None of the task appears

svl
2015-05-18
2016-07-26
  • svl

    svl - 2015-05-18

    I am using the latest version 4.0.

    I have created the project called "PROJECT01" and created all the tasks. After I reopen the task , I am unable to see the tasks. It throws the error as

    Error:

    can't read "row(tree_order)": no such element in array

    Kindly help me out.

     
  • Klaus Hofeditz

    Klaus Hofeditz - 2015-05-18

    I once experienced this err message related to a memory issue. Can you try to restart the webserver before we have a closer look?

     
  • svl

    svl - 2015-05-19

    Hi Klaus,

    As you said, I restarted the server and tried. Again the same error.

    Timesheet Tasks

    Error:

    can't read "row(tree_order)": no such element in array

    Help me please.

     

    Last edit: svl 2015-05-19
  • Frank Bergmann

    Frank Bergmann - 2016-07-26

    Hi!

    We would need to reproduce this issue in order to be able to fix it. We've checked for "tree_order", but that only appears on a deep-down system routine.

    The most likely cause is that you did something strange in the definition of your tasks, thus creating an exceptional situation that's not handled by the system routine.

    => Please send use the MS-Project schedule that you imported or try to reproduce on one of our demo servers.

    Sorry, we can't help more...
    Frank

     

Log in to post a comment.