How to add the resource to the planning taking account its work time

Help
2014-01-31
2014-02-10
  • Hello,

    I am planning a project with openproj and I wonder if it is possible to automatically manage when one resource is taking part of most of the tasks so they won't be able to do at the same time and might be create a kind of dependency but because the time, not the task (FS, FF, ...)

    If not, I concatenate one task after the other but they have not real dependencies so I don't think this is the best way.

    Can anybody clarify me if this is possible and how to do it in that case?

    I hope to make myself understand.

     
  • Hello,

    I have a similar problem.
    I try to plan a disaster recovery plan. Some people are assigned to 6 or 7 tasks at the same time. Obviously this can't work. So, I'd like to prioritize the tasks and if a resource is overcommitted the tasks are scheduled according their priority.

    I don't think this is possible yet. But maybe you put that on your list of ideas for future enhancements.

    Regards
    Bernhard