Need help with resources and percentages

Help
Stars
2013-10-02
2013-10-02
  • Stars
    Stars
    2013-10-02

    I'm new to OpenProj. I've created four tasks and, in the first two, when I put myself down as a resource at 50%, the two-day tasks turn into four days. Perfect. In the next two, I'm doing the exact same thing (putting me down at 50%) but the two-days tasks remain at 2 days. No matter what resource I put in that field (whether I change it to someone else's name or not) and no matter which percentage I select, the duration doesn't change! Can anyone help?!