#207 Working calendar does not change

v1.0 (example)
open
nobody
None
5
2012-01-28
2012-01-28
Anonymous
No

When I change the working calendar, changes are not made in my calendars, and when I go into the "Change Working Calendar" window, the same "Standard" option is selected. Any new calendar I create is not saved when I close and open openproj again.

Discussion


  • Anonymous
    2012-05-23

    Hi,

    all what you have to do is to check the "Ignore resource time" box, as your calendar and the resource's are conflicting.

    I worked with me :-)

    B,

     

  • Anonymous
    2012-05-23

    Hi,

    all what you have to do is to check the "Ignore resource time" box, as your calendar and the resource's are conflicting.

    I worked with me :-)

    B,

     
    Last edit: Anonymous 2014-02-23
  • Tahoeob
    Tahoeob
    2012-07-23

    Hi Martin, I just posted a note on the pending release of ProjectLibre which will fix the issues you are having. We are hosting ProjectLibre on SourceForge as well. We were the founders and developers of OpenProj and happy to be updating it...............

    * Bug fixes (many, many, many)
    * Microsoft Project Import/Export fixed
    * Printing being added
    * other items