#354 Workday hours need to be per-resource

open
nobody
Other (25)
5
2012-07-18
2009-01-06
Brian Bober
No

Our company works internationally and the usage case is that workday hours are different for European resources than U.S. resources so we are essentially forced to use the same hours for all international resources and then remember in our head that 6 o'clock PM for Dresden means they will be done at 12 o'clock our time. For projects that we are combining resources internationally on a critical short project where the European side picks up work where the U.S. leaves off and vice-versa, the Gantt Chart doesn't reflect that.

I don't think this is a major issue because calculations still seem to be accurate, however it would be a nice-to-have for the future.

Discussion