#168 open an older project

added_in_1.11
closed
nobody
5
2012-07-18
2005-03-19
THOMAS Alexandre
No

Open an older project should automaticaly set the week
end at saturday and sunday. Because no week are setting
and the chart do not include some gray columns on the
week end

Discussion

  • Logged In: YES
    user_id=162766

    Alexandre, I do not agree. IMHO user wishes to schedule his
    project and do it correctly, rather than to see grey columns
    which mean nothing. He also don't want our tool to affect
    his project if he doesn't want project to be affected. If we
    open old project (which de-facto has no weekends) and add
    weekends automatically without any questions than we
    probably corrupt that project. If user wants to apply
    weekends to old project, he will import it (it works!)