#154 Defining task charge instead of delay

closed
nobody
5
2012-07-18
2005-01-14
Eric Colleu
No

It would be usefull to define time charge on a task
instead of delay.
For example if I define 5 days of charge for a task, and if
the ressource affected to this task works with 80% of
occupation, the calculated task delay will be 6 days.

Discussion

  • Peter
    Peter
    2005-04-20

    Logged In: YES
    user_id=1263320

    This is the most important feature that this great software is
    missing. Projects always include tasks that are done 100%
    of the day.