Typical! You wait a whole year for a new MPXJ release, the two come
along in the space of one month!
This is mainly a bug fix release, the only significant new
functionality is the implementation of more resource assignment
attributes, as noted below.
Cheers!
Jon
>From the change log:
Added support for resource assignment fields Baseline Cost 1-n,
Baseline Work 1-n, Baseline Start 1-n, Baseline Finish 1-n, Start 1-n,
Finish 1-n, Date 1-n, Duration 1-n, Cost 1-n, Text 1-n, Number 1-n,
Flag 1-n, for MPP, MPD, and MSPDI files.
Added support for task suspend date, task resume date, and task code
read from Primevera, and represented in MS Project custom fields
Date1, Date2, and Text1 respectively.
Added support for retrieving the table associated with any view.
Updated to fix SourceForge bug 3317333: Error converting Mpp to planner.
Updated to fix SourceForge bug 3316806: MSPDI Linklag for TimeUnit.Percent.
Updated to fix SourceForge bug 3316419: Error reading calendars for
2010 files.
Updated to fix SourceForge bug 3323027: Duplication of calendar id.
Updated to fix SourceForge bug 3310996: Wrong task start.
Updated to fix SourceForge bug 3308542: Wrong start and finish dates
for 2010 files.
|